CAMPUS CONSTRUCTION

Campus Construction Update

October 2016 Inscribed

Property development at Yellowstone Theological Institute’s future Bozeman campus is steadily underway.

[Click images to view]

Stucky Road, part of the expansion of 19th, and the laying down of infrastructure has been completed going to the property, and all the roads have been opened back up for regular traffic in the area of South Bozeman.

The process of laying infrastructure along Graf Street, which will cut through the property, is the current focus, and the road construction itself will begin once that is completed.

Currently, the plan is for roads to be completed by April 2017; we will then break ground on building construction in June 2017.

This process, phase one of the center’s construction, is set to be finished in late 2018.